project references

North Ireland water treatment plant

Source and ©: https://greencells.com/en/greencells/references

facts

location: dunore point north ireland

construction january - march 2018

capacity: 6,582.24 kWp (23.508 modules)

production per year: 5,673,890.88 kWh

own-consumption per year:  4,749,046.67 kWh (83.7%)

 

scope of work pv-c: epc and o&m negotiations, major components   selection and negotations

 

 

Segmueller furniture retail store and warehouse

Source and © : https://www.ib-bestler.de/projekte/weiterstadt

facts

location: weiterstadt (germany)

construction juni – august 2014

capacity: 1,009.80 kWp (3.960 modules)

production per year: 971,904.38 kWh

own-consumption per year:  898,039.64 kWh (92.4%)

 

scope of work pv-c: project development, load profile modeling, epc and o&m negotiations, major components selection and negotations

 

 

Ploetzin cold storage warehouses

Source and ©: pv-contracting (Thomas Freyberg)

facts

location: ploetzin (germany)

construction: july 2011

capacity: 299.7 kWp (1.332 modules)

production per year: 252,274.4 kWh

own-consumption per year:  243,576.8 kWh (96.4%)

 

scope of work pv-c: spa negotiations, due diligence, financial modeling

 

client references

scope of work pv-c advisory for "technologie into market"

 

 

scope of work pv-c: project co-developments in Europe and Latin America; HR advisory

 

 

 

 

 

scope of work pv-c:  load-profile and finanical modeling

 

 

 