lower austrian agri-pv project development

facts

location: wilfersdorf (lower austria)

development duration 2021 - 2026

capacity: 10,270 Wp (16,302 modules)

 

envisaged production per year: ~12,323 MWh

 

agricultural part:  75%

 

scope of work pv-c: development finance, investor origniation, M&A

 

 

albanian project development diber

 

facts

location: diber (north albania)

development duration: 2024 - 2026

capacity: 99 MWac

 

envisaged production per year: ~168,000 MWh

 

scope of work pv-c: project co-development management

 

 

canandian large utility scale project development 

facts

location: dunmore (south east alberta - canada)

development duration: 2022 - 2026

capacity: 216 MWac

envisaged production per year: ~430,000 MWh

agricultural part:  80%

envisaged data-center connection and consumption for 100% of power produced 

 

scope of work pv-c: project co-development management, investor & PPA origination, grid-connection coordination, co-investor management

 

North Ireland water treatment plant

Source and ©: https://greencells.com/en/greencells/references

facts

location: Dunore Point (North Ireland)

construction january - march 2018

capacity: 6,582 kWp (23.508 modules)

 

production per year: ~5,674 MWh

 

own-consumption per year:  ~4,750 MWh (84%)

 

scope of work pv-c: project co-development, epc qualification, epc and o&m negotiations, major components selection and negotiations

Segmueller furniture retail store and warehouse

Source and © : https://www.ib-bestler.de/projekte/weiterstadt

facts

location: Weiterstadt (Germany)

construction june – august 2014

capacity: 1,010 kWp (3.960 modules)

production per year: ~972 MWh

 

own-consumption per year:  ~923 MWh (95%)

 

scope of work pv-c: project development, load profile modelling, epc and o&m negotiations, major components selection and subcontractor qualification

Al-Ahliyya Amman University

Source and ©: pv-contracting (Thomas Freyberg)

facts

location: Amman (Jordan)

construction: july 2014

capacity: 276 kWp (1.332 modules)

production per year: 452 MWh

 

own-consumption per year:  397 MWh (87%)

 

scope of work pv-c: EPC negotiations, due diligence,

client references

scope of work pv-c utility scale project development advisory and support

 

 

scope of work pv-c:   project development, origination, M&A and transaction advisory

 

 

scope of work pv-c: partner- and business development advisory

 

scope of work pv-c advisory in terms of "technology into market"

 

 

scope of work pv-c: project co-developments in Europe and Latin America - HR advisory

 

 

 

 

 

scope of work pv-c:  project origination and M&A advisory

 

 